What mould to use for +100'c

http://www.talkcomposites.com/Topic13493.aspx

By richardstock - 10/30/2014 11:40:38 AM

I have finally finished my 2m x 2m x 2m oven with internal vac lines etc and plan to start to use Easy-Preg Surface Layer and Vari-Preg pre-preg carbon fiber material.

I understand that the Easy-Preg needs to be cured at 100'c > however the Unimold system is rated up to 90'c

What would be the ideal mould to use for this?
By richardstock - 10/31/2014 11:43:03 AM

Warren (Staff) (31/10/2014)
We have had a couple of customers say they have got higher temperatures with Uni-Mould than the data suggests.  We are going to do some additional tests, in the next few weeks, with an old mould and some pre-preg to see how high we can go with the system.


That would be fantastic Smile